The Mines Act 1952
1 / 130
1. Which are the Mines in India where the Mines Act 1952 are applicable?
2 / 130
2. When was the Mines Act formulated?
3 / 130
3. Which Act was applicable to the mines in India before the Mines Act 1952?
4 / 130
4. How many sections are there in Mines Act 1952? (sec 01)
5 / 130
5. Mines Act 1952 is applicable to? (sec 01)
6 / 130
6. Under the Mines Act What is the definition of adult? What will be the age of a adult person? (Section - 2)
7 / 130
7. What does the Agent do? (Section - 2).
8 / 130
8. According to the Mines Act what is the definition of a "day"?
9 / 130
9. What is the meaning of Office in a Mine? {Section - 2}
10 / 130
10. Reportable Accident Means? What is the meaning of reportable accident? {Section - 2}
11 / 130
11. Meaning of a week?{Section - 2}
12 / 130
12. If any injury which involves; or in probability will involve the permanent loss of any part or section of a body or the use of any part or section of a body, or the permanent loss of or injury to the sight or hearing or any permanent physical incapacity or the fracture of any bone, then which type of injury is this?{Section- 2}
13 / 130
13. Where the Mines Act won't apply? {Section - 3}
14 / 130
14. Referring to the time of day (When does the time of day start? (Section - 4)
15 / 130
15. Chief Inspector appointed by? {Section - 5}
16 / 130
16. By whom inspector of mines is appointed?
17 / 130
17. Chief Inspector or Inspector Discharge his powers under which law (Section 7)
18 / 130
18. Before going to a mine, notice is given to mine manager how many day's before entering into the mine? (Section - 8 )
19 / 130
19. Committee in Mines are formed under which section?
20 / 130
20. What will be the total number of members in a Committee?
21 / 130
21. The Chairman of the Commeittee is appointed by whom? (Section 12)
22 / 130
22. Constitution of the Committee under the Mines Act 1952 is formed by? {Section - 12}
23 / 130
23. Who shall bear the expenses of the Committee set up by the Central Government? {Section - 15}
24 / 130
24. Notice of mining operation by Manager/Owner/Agent to be given to whom? (Section 16)
25 / 130
25. Before starting Mining Operation, Manager/Owner/Agent - shall give notice ti CI _______ days before commencement of operation (Section 16)
26 / 130
26. Whether the Owner, Agent who has the qualification of Manager, can appoint himself as manager? {Section - 17}
27 / 130
27. What shall be the distance between the drinking water arrangement and toilet/latrine/urinal?
28 / 130
28. Fore how many persons, the drinking water shall be effectively cooled by mechanical or other means?
29 / 130
29. The scale of latrine accommodation shall be at least one seat for every ____persons(Section 20.)
30 / 130
30. First Aid rooms shall be provided at every mine employing more than _____ persons on any one day. (Section 21)
31 / 130
31. First Aid stations shall be provided at every mine employing more than ____ persons on any one day {Section - 21}
32 / 130
32. Power to Prohibit Employment in Certain Cases Come Under Which Section of the Mines Act 1952?
33 / 130
33. If there is an accident in mines, For how many days the notice of the accident shall be kept on the notice board? (Section - 23)
34 / 130
34. If any incident (Reportable) or near-miss occured in a mine, then within how many days will the record be sent to the Chief Inspector? (Section - 23)
35 / 130
35. Where a notice given under sub-section(1) relates to an accident causing loss of life, the authority shall make an inquiry into the occurrence within how many days? (Section - 23))
36 / 130
36. A copy of the entries in the register referring to an incident shall be sent to the CI by the owner, agent or manager of the mine, in which date? (Section - 23)
37 / 130
37. Where the Chief Inspector or any Inspector fails to inspect the place of accident, within ________ hours of the time of the accident, work may be resumed at the place of the accident. (Section - 23)
38 / 130
38. In Which Of The Following Cases, Place Of Accident Not to Be Disturbed ?(Section - 23)
39 / 130
39. The power of the Government to appoint a court of enquiry in cases of accidents is mentioned in which section of the Act?
40 / 130
40. Court of enquiry is constituted by? {Section - 24}
41 / 130
41. Whome to submit the report after an investigation by the Court Of Inquiry ? {Section - 24}
42 / 130
42. Who are responsible for producing all documents as required by the Court of Inquiry? {Section - 24}
43 / 130
43. Where any person employed in a mine contacts any disease notified by the Central Government in the official Gazette as a disease connected with mining operations the O/A/M of the mine, as the case may be, shall send notice thereof to the Chief Inspector within how many days (Section - 25)
44 / 130
44. Weekly Day Of Rest Means (Weekly Rest) ? (Section 28.)
45 / 130
45. If any person deprived of any of the weekly days of rest, he shall be allowed to take it within how many days? {Section - 29}
46 / 130
46. As per Mines Act, no persons shall be allowed to work for more than how many hours in a day? {Sec- 30}
47 / 130
47. As per Mines Act, no person shall be allowed to work for more than how many hours in a week ? (Section- 30 )
48 / 130
48. In Emergency Conditions, maximum how many hours a person can work? {Section - 30}
49 / 130
49. Any person shall not work for more than _____ hours continuously before he has had an interval for rest of at least ____ hour: {Section - 30}
50 / 130
50. After how many continuous hours of work any person should take rest of 30 minutes? {Section - 30}
51 / 130
51. No person employed below ground in a mine shall be allowed to work for more than ____ hours in a day. {Section - 31}0}
52 / 130
52. As per the Mines Act - 1952, in Under Ground, how many more hours can be worked in a week in Mines? {Section - 31}
53 / 130
53. A weekly day of rest shall mean in his case a period of ____ consecutive hours beginning when his shift ends {Section - 32}
54 / 130
54. After how many hours of work on the surface, overtime shall be given? {Section -33}
55 / 130
55. No person shall be required or allowed to work in a mine if he has already been working in any other mine within the preceding ____ hours. {Section - 34}
56 / 130
56. Maximum number of hours a person can work including overtime (Section 35)
57 / 130
57. How is overtime calculated?
58 / 130
58. How many days before the commencement of work, the notice of 'hours of work' shall be posted on notice board? {Section - 36}
59 / 130
59. What is the minimum age of Apprentice/Trainee in Mines? (Section 40 )
60 / 130
60. After the amendment of the Act in 1983, what shall be the minimum age of persons who shall be allowed to work in any mine or part thereof?(Section - 40}
61 / 130
61. Prohibition of the presence of persons below eighteen years of age in a mine is mentioned in which section of the Act?
62 / 130
62. What is the time of employment for deploying a woman in a mine (Section 46.)
63 / 130
63. Notwithstanding anything contained in this Act, no employment of any woman is permitted in between?
64 / 130
64. Every woman employed in a mine above ground shall be allowed an interval of not less than e_________ between the termination of employment on any one day and the commencement of the next period of employmen { Section - 46}
65 / 130
65. Attendance Record of Persons Employed in Mines shall be recorded in which form ? {Section - 48
66 / 130
66. In which section definition of leave is there?{Section - 50}
67 / 130
67. According to Mines Act 1952 what is  "Calenender Year"? {Section- 51}
68 / 130
68. In the case of a person employed below ground, at the rate of one day for every _____ days of work performed by him, leave shall be credited {Section - 52}
69 / 130
69. In the case of a person employed on the surface, at the rate of one day for every _______ days of work performed by him, leave shall be credited {Section - 52}
70 / 130
70. A calendar year’s service shall be deemed to have completed, if he/she works {Section - 52}
71 / 130
71. How many days of Maternity Leave does a female employee get?{Section - 52}
72 / 130
72. A person employed in a mine shall inform the manager, how many days before taking a leave?{Section - 52}
73 / 130
73. How many times in a Calendar Year, a person employed in Mines can take leave? {Section - 52}
74 / 130
74. The total number of days of leave which may be accumulated by any such person shall not at any one time exceed ?{Section - 52}
75 / 130
75. For the leave allowed to a person employed in a mine under section 52, he shall be paid at a rate equal to the _______ of his total full-time earnings for the days on which he was employed during the month immediately preceeding his leave {Section - 53}
76 / 130
76. Any person employed in a mine who has been allowed leave for not less than ______days shall before his leave begins be paid the wages due for the period of the leave allowed. {Section - 54}
77 / 130
77. Under which section of the Mines Act, Regulations are made? (Section- 57)
78 / 130
78. If the surface has "Railway Line, Building, Structure", how many meters of pillar shall be left at that place?
79 / 130
79. In which year was the Indian Explosive Act made?
80 / 130
80. When was the Railway Act made?
81 / 130
81. Mines Rule 1955, under which section of the Mines Act, it has been made? (Section - 58)
82 / 130
82. The mines wherein any women employed or were employed on any day of the preceding twelve months of suitable rooms to be reserved for the use of children under the age of _____years (Section - 58)
83 / 130
83. A shelter shall be made if how many people are employed in Mines? {Section - 58}
84 / 130
84. Canteen shall be made, if how many persons employed in a mine? {Section - 58}
85 / 130
85. Welfare officer shall be employed, if how many persons are employed in a mine? {Section - 58}
86 / 130
86. If 1000 people are working in a mine, then in that mine, how many canteens will be made? {Section - 58}
87 / 130
87. Under which section of the Mines Act, By - Law has been made?
88 / 130
88. By - Laws are made by whom? (Section - 61)
89 / 130
89. What are the information generally By-Laws provide? (Section- 61)
90 / 130
90. After approving the 'By-laws' by the mine manager, to whom it has to be sent? (Section - 61)
91 / 130
91. Within how many days, the by-laws has to be sent to CI by O/A/M? (Section - 61)
92 / 130
92. Mine Act, Regulation, Rules are made by whom? (Section - 61A)
93 / 130
93. If any person obstructs to discharge the duties by Chief Inspector or Inspector what shall be the punishment? (Section - 63)
94 / 130
94. If any person refuses to provide Register or Document to the Chief what shall be the punishment (Section - 63(2)
95 / 130
95. What is the punishment mentioned in the Act for falsification of records or certificates? (Section - 64)
96 / 130
96. What is the punishment for using false certificate of fitness? (Section - 65)
97 / 130
97. Punishment for omission to furnish plans without any reason? (Section - 66)
98 / 130
98. Punishment for prohibiting/ retricting or regulating the employment or presence of persons in or about a mine(Section- 67}
99 / 130
99. What shall be the penalty for employment of person below 18 years of age? (Section - 68)
100 / 130
100. What shall be the punishment in contravention of the provisions of section 17, if fails to appoint a manager(Section - 69)
101 / 130
101. Whoever in contravention of the provision of sub-section (1) of section 23 fails to give notice of any accidental occurrence or to post a copy of the notice on the special notice board referred to in that sub-section and to keep in there for the period specified shall be punishable with__________? (Section - 70)
102 / 130
102. If O/A/M fails to record in the prescribed register to give notice of any accidental occurrence shall be punishable with ______?(Section - 70)
103 / 130
103. Where the owner, agent or manager of a mine, as the case may be, has taken proceeding under this Act against any person employed in or about a mine in respect of an offence under this Act, he shall within _________ days from the date of the judgement or order of the court report the result thereof to the Chief Inspector (Sec - 71)
104 / 130
104. Which punishment shall be imposed for violating section 22 or 22 A? (Sec. - 72B)
105 / 130
105. Punishment for willfully neglect the arrangement of the provisions for the purpose of securing the health or safety of the persons employed therein(Section 72(c)
106 / 130
106. Special provision for contravention of law with dangerous results- if in such contravention results in loss of life, then what shall be the punishment?(Section 72(c)
107 / 130
107. Special provision for contravention of law with dangerous results- If such contravention results in serious bodily injury, then what shall be the punishment? (Section - 72C)
108 / 130
108. Special provision for contravention of law with dangerous results- If such contravention results in small injury, then what shall be the punishment? (Section - 72C)
109 / 130
109. Where a person having been convicted under section 73 is again convicted thereunder, shall be punishable with_____?
110 / 130
110. Where the owner, agent or manager of a mine, accused of an offence under this Act, alleges that another person is the actual offender, he shall be entitled, upon complaint made by him in this behalf and on his furnishing the known address of the actual offender and on giving to the prosecutor not less than __________days notice in writing of his intention to do so, to have that other persons brought before the court (Section - 77)
111 / 130
111. When O/A/M fails to comply with the order of the court made under section 78, what shall be the punishment? (Section - 78)
112 / 130
112. Act, Regulation or Rules are made by whom?
113 / 130
113. Who can make changes in the Act, Rules, Regulations?
114 / 130
114. Under section 57, provisions for which regulations have been made?
115 / 130
115. Provisions for which regulations have been made in section 58
116 / 130
116. Whose responsibility is to comply with the rules and regulations under mines act?
117 / 130
117. Reportable Injury means?
118 / 130
118. What does an Agent do?
119 / 130
119. What kind of medical examination is done before joining the mine? (Page -96)
120 / 130
120. Interval of PME? (Page - 96)
121 / 130
121. PME for the persons o above 45 years' of age? (P- 96)
122 / 130
122. PME for a person having age of 67 years? (P- 96
123 / 130
123. HEMM Operator's vision test is required in every _________ years?
124 / 130
124. Within how many years, PME should done for the persons employed in asbestos mines?
125 / 130
125. What type of equipment are mandatory in the PME Center?
126 / 130
126. What are the notified diseases?
127 / 130
127. If the worker working in Mines has any of the Notified Diseases, then within how many days,the O/A/M shall report it to proper authority?
128 / 130
128. The O/A/M shall report to whom, regarding the detection of notified diseases in his mine?
129 / 130
129. On how many people working in Surface Or Open Cast Mine? cold water shall be arranged?
130 / 130
130. Provision of shelter over how many people ordinarily employed in Mines?
Your score is
The average score is 52%
Share
Restart quiz Exit
The Mines Rules 1955
1 / 118
Category: The Mines Rule 1955
1. The registers of reportable injury and minor accidents shall be maintained in which form?
2 / 118
2. What shall be the minimum basic pay of a welfare officer?
3 / 118
3. If a welfare officer is unable to perform his duties, the O/A/M can appoint another person whom he considers competent, but maximum how many days that person can act as welfare officer?
4 / 118
4. After the appointment of a Welfare officer by O/A/M, within how many days the notice shall be sent to Chief inspector?
5 / 118
5. No person shall act as welfare officer of a mine unless he possesses -
6 / 118
6. For how many persons ordinarily employed in a mine, one additional welfare officer shall be deputed, and at what scale?
7 / 118
7. For how many persons ordinarily employed in a mine, provision for welfare officer is there?
8 / 118
8. The terms of office of the elected members for canteen managing committee shall be ?
9 / 118
9. How many members can be there in a canteen managing committee?
10 / 118
10. What shall be the scale of members in a canteen managing committee?
11 / 118
11. Who can nominate the members of canteen managing committee?
12 / 118
12. At what frequency, the canteen managing committee shall consult the matters related to the canteen?
13 / 118
13. The inside walls of kitchen of canteen shall be painted at what frequency?
14 / 118
14. The wood work or iron structures shall be painted at what frequency?
15 / 118
15. At what frequency, the inside wall of a canteen shall be white washed?
16 / 118
16. The canteen shall be situated ______m away from any latrine, urinal, boiler house etc.
17 / 118
17. Provisions of the canteen for how many persons are ordinarily employed in a mine?
18 / 118
18. What shall be the height of the roof in a shelter of a mine if the roof is a sloping one?
19 / 118
19. If the roof of a shelter in a mine is of flat roof, the what should be its height?
20 / 118
20. Evry shelter in a mine shall have a floor area of ?
21 / 118
21. provision of shelter for how many persons ordinarily employed in a mine?
22 / 118
22. On which day of the year, the O/A/M of a mine shall exhibit on the notice board at the office, information regarding leave with wages?
23 / 118
23. For how many days the register of leave with wages shall be preserved?
24 / 118
24. Register of Leave with wages shall be maintained in which form?
25 / 118
25. Can an apprentice or trainee below 18 years of age be employed in a mine ?
26 / 118
26. As per the mines rules 1955, termination of employment shall be maintained in which form?
27 / 118
27. As per The Mines Rules 1955, the register of compensatory days of rest shall be maintained in which form?
28 / 118
28. Which of the following shall not be deemed to be a person holding a position of supervision or management or employed in a confidential capacity-
29 / 118
29. In every open cast working, one first aid station for how many persons shall be provided?
30 / 118
30. At every mine employing more than _____ persons on any one day, there shall be provided a suitable first aid room.
31 / 118
31. On or before the ______ day of every month, there shall be displayed on a notice board outside the office of the mine a list of all persons who have not been allowed compensatory days of rest during that month, and the dates on which compensatory days of rest will be allowed to them in the following _______months.
32 / 118
32. As per the Mines Rules 1955, the weekly day of rest shall be maintained in which form?
33 / 118
33. In which case the weekly day of rest shall be posted on conspecuous places?
34 / 118
34. For the purpose of sections 28 and 29, a day of rest for any person shall mean period of rest of at least ______ consecutive hours.
35 / 118
35. The first aid room shall be in charge of a qualified medical practitioner, where the number of persons ordinarily employed in a mine is more than?
36 / 118
36. What are the equipment shall be provided in a first aid room?
37 / 118
37. How much floor space should be available in a first aid room?
38 / 118
38. For how many persons ordinarily employed in a mine, first aid room shall be provided?
39 / 118
39. Availability of First Aid personnel shall be-
40 / 118
40. Receptacles and night soils shall be cleaned and disinfected at least once in every?
41 / 118
41. What shall be the scale of latrines inside underground?
42 / 118
42. The interior walls and ceiling of latrines shall be white washed once at least ?
43 / 118
43. Upto what height, the walls of latrines hall be cement punned?
44 / 118
44. What shall be the scale of latrines and urinals?
45 / 118
45. For how many persons are employed in a mine, drinking water shall be effectively cooled?
46 / 118
46. The quantity of drinking water to be provided in a mine or a mine or any part thereof shall be on a scale of at least ______ ltrs for every person employed at any one time.
47 / 118
47. Within how many days, O/A/M shall implement the recommendations of Safety Committee?
48 / 118
48. At what interval safety committee members shall meet?
49 / 118
49. Which of the following shall be the function of the safety committee?
50 / 118
50. Total how many persons will be there in the safety committee?
51 / 118
51. Safety committee shall be constituted by O/A/M, if how many persons are ordinarily employed in that mine?
52 / 118
52. The safety committee un der Mines Rules 1955, shall be constituted by whom?
53 / 118
53. Within how many days, O/A/M shall take action on the report of Workmen's inspector?
54 / 118
54. In which form, Workmen's inspector shall record his inspection report and observation?
55 / 118
55. Which of the following shall not be the duty of a Workmen's inspector?
56 / 118
56. A workmen's inspector nominated under rule 29 Q shall hold office for a period of __________ years from the date of his nomination.
57 / 118
57. Who shall afford all the reasonable facilities to Wormen's inspector making entries, inspection, measurement, examination etc?
58 / 118
58. In a week, how many days the workmen's inspector shall perform his duties as a Workmen's inspector?
59 / 118
59. How many lectures of training is required for a Workmen's inspector?
60 / 118
60. How many years of experience are needed in that particular mine where a person shall be designated as a Workmen's inspector?
61 / 118
61. How many years of experience in mines is required to be a workmen's inspector?
62 / 118
62. No person shall act as a workmen's inspector of a mine unless- he possess an _____________ certificate
63 / 118
63. For which of the following, workmen's inspector shall not be designated??
64 / 118
64. If in a mine the total no of ordinarily employed persons are 2500 then how many workmen's inspector shall be designated in that mine?
65 / 118
65. If in a mine the no of ordinarily employed persons are 1400, then how many workmen's inspector shall be designated?
66 / 118
66. Consultation shall be done with whom, before designating Workmen's inspector by O/A/M?
67 / 118
67. For how many persons are ordinarily employed in a mine, Workmen's inspector shall be designated in that mine?
68 / 118
68. Details of Workmen's inspector is mentioned in which rule of Mines Rules 1955?
69 / 118
69. If a mine is abandoned or discontinued for a period of more than sixty days or if ownership has been changed, then when the annual return of medical examination/ re-examination shall be submitted?
70 / 118
70. Annual return of medical examination/re-examination and other details shall be filled in which form and when is it to be sent to the Chief Inspector?
71 / 118
71. Cost of medical examination shall be borne by?
72 / 118
72. When Workmen's Compensation Act was formed?
73 / 118
73. Medical certificate of re-examination done by appellate medical board shall be filled in which form?
74 / 118
74. Medical re-examination of appellant shall be done according to which standard?
75 / 118
75. How many medical officers shall be there in the appellate medical board?
76 / 118
76. In which rule Constitute of medical appellate board, is mentioned?
77 / 118
77. Medical re-examination of a person who appealed for the re0examination, shall be done by-
78 / 118
78. In which form the manager shall give notice to appellant of medical re-examination?
79 / 118
79. Before how many days, manager shall give notice to appellant of medical re-examination under rule 29 J?
80 / 118
80. Within how many days, the manager shall arrange for a medical re-examination of a person who has appealed under rule 29 J?
81 / 118
81. Within how many days, a medical re-examination appeal can be done by a person?
82 / 118
82. What shall be the period of retention for medical certificates of persons employed in a mine?
83 / 118
83. Copy of the medical certificate shall be mentioned in which form?
84 / 118
84. Which standard shall be followed for IME or PME?
85 / 118
85. Within how many days the Chief Inspector shall be liable to give his decision if any dispute arises from mine management reading the PME of person?
86 / 118
86. In case of any dispute in between the mine management and the person employed, the same shall be referred to whom?
87 / 118
87. What shall be done if a person fails to submit himself for medical examination even after two consecutive notice as per the guidelines under The Mines Rules 1955?
88 / 118
88. A person who fails to submit himself for medical examination shall be given a second notice of minimum period of _________ days in form ______.
89 / 118
89. Notice of medical examination by mine manager shall be given in which form?
90 / 118
90. In respect of any medical examination under Rule 29B, the manager of a mine shall give at least _________ days prior notice inw writing to the person.
91 / 118
91. The medical examination under IME or PME shall be carried out by a medical officer appointed by ?
92 / 118
92. All the test reports of PME shall be recorded in which form?
93 / 118
93. In case of an asbestos mine, at what interval X-ray examination shall be done for the persons employed in the mine?
94 / 118
94. In the case of asbestos mines, what shall be the interval for PME?
95 / 118
95. At what interval, periodical medical examination(PME) shall be done for a person employed in a mine?
96 / 118
96. For the initial medical examination of every person seeking employment in a mine, unless such person has already undergone within the preceding ______ years a medical examination under the guideline of The Mines Rules 1955 while employment at another mine.
97 / 118
97. In which of the following cases, medical examination shall not be applied?
98 / 118
98. If any person sent up for medical examination in pursuance of sec 43 is not certified to be fit by the certifying surgeon he shall not without the permission in writing of an inspector be sent for another medical examination unless a period of ____________ months has elapsedfrom the time when he was last sent up for medical examination.
99 / 118
99. If a court of inquiry finds, the accident was due to the carelessness or negligence of mine management then from where the expenses shall be recovered
100 / 118
100. Court of enquiry is mentioned in which rule of The Mines Rules 1955?
101 / 118
101. Who shall circulate the minutes of the meeting done amongst committee members?
102 / 118
102. At any meetings amongst Committee, in which less than 4 members are present, the chairman may adjourn the meeting to a date not less than?
103 / 118
103. No business shall be transacted at a meeting of the committee unless at least ________ members including the chairman are present.
104 / 118
104. For Notice of meeting amongst the committee members, the secretary to the committee shall give at least ______ days notice to every members.
105 / 118
105. For how long a member of the Committee under rule 4 of mInes Rules 1955, can be absent from India?
106 / 118
106. What shall be the expiry period of the resignation given by any member of the Committee under rule no 4 of Mines Rules 1955?
107 / 118
107. Who shall nominate the secretary of the committee under rule no 4 of Mines Rules 1955?
108 / 118
108. What shall be the terms of office for the committee under rule 3 of Mines Rules 1955?
109 / 118
109. How "ordinarily employed" is calculated?
110 / 118
110. Ordinarily employed means?
111 / 118
111. Officer-inc-charge-canteen means?
112 / 118
112. Who is a certifying surgeon?
113 / 118
113. Who is a manager and appointed by whom?
114 / 118
114. Form means?
115 / 118
115. Court of enquiry is mentioned in which section of the Mines Act 1952?
116 / 118
116. In which mines, The Mines Rules 1955 is applicable?
117 / 118
117. In exercise of the powers conferred by section ________ of the Mines Act, 1952, the central gove has made Mines rule 1955?
118 / 118
118. Under which section of the Mines Act 1952, The Mines Rules 1955 has been made?
The average score is 3%
Restart quiz
MMR 1961: Q & A
A total of 365 question and answers are there in this quize.
1 / 321
Metalliferous Mines Regulation 1961 came into force for which mines? {Regulations - 1}
2 / 321
Metal Mines Regulation 1961 came into force under which section of the Mines Act 1952 ? {Reg.- 1}
3 / 321
Approved Safety Lamp and Safety Torch are Approved by whom? {reg. - 2}
4 / 321
Assistant Manager does the following work? { reg. - 2}
5 / 321
What is Auxillary Fan? {reg. - 2 }
6 / 321
Where the banksman is appointed?
7 / 321
Where the bellman is appointed?
8 / 321
As per MMR 1961, Blaster comes under which category? { reg. - 2}
9 / 321
What should be the minimum age of a competent person? { reg. - 2}
10 / 321
Which Act should you refer to, when the term 'Explosive' comes into the picture? { reg. -2 }
11 / 321
Face Means ? {Reg. - 2}
12 / 321
Landing Means ? {Reg. - 2}
13 / 321
Manager means a person appointed under which section of the Mines Act 1952?
14 / 321
The manager is appointed by whome?
15 / 321
Duties of a mine foreman, as per MMR? {reg. - 2}
16 / 321
Misfire Means ? { Reg. - 2}
17 / 321
Permitted Explosives are approved by? {reg. - 2}
18 / 321
Quarter Means ? {Reg. - 2}
19 / 321
Railway Means given by the Indian Railway Act _ _ _ _ _ _ _ _? {reg. - 2}
20 / 321
Regional Inspector Means ? {Reg. - 2}
21 / 321
A shot-hole or part of a shot-hole remaining after being charged with explosive and blasted, which is not a misfired shothole is called?
22 / 321
Winze Means ?
23 / 321
Raise Means ? {Reg.- 2}
24 / 321
Notice of Opening is mentioned in Which Regulation ?
25 / 321
In which form Notice of Opening to be sent by the Manager to the Chief Inspector or to the Regional Inspector? {reg. - 3}
26 / 321
If any changes are made in the Mine Boundary then, then within how many days, the manager shall give the notice to the Regional Inspector? {reg. - 3}
27 / 321
After opening a mine, within how many days should be reported to the regional inspector and chief inspector? {reg. - 3}
28 / 321
The notice of opening to be sent to whom by the O/A/M? {reg. - 3}
29 / 321
When will the Manager, Owner, Agent give notice of Quarterly Return? {reg. - 4}
30 / 321
In which form, are the Quarterly Returns to be sent? { reg. - 4}
31 / 321
In which form the Annual Returns is filled? {reg. - 4}
32 / 321
On which date the Annual return is to be filed by the O/A/M? {reg. - 4}
33 / 321
If a change occurs in the ownership of a mine, the annual returns required under MMR shall be submitted within how many days {reg. - 5}
34 / 321
If a mine is abandoned or working thereof is discontinued for a period exceeding 60 days, then within how many days annual return to be filed? {reg. - 5}
35 / 321
When it is intended to abandon a mine or to discontinue working thereof for a period exceeding four months, the owner, agent or manager shall, not less than _________days before such abandonment or discontinuance, {reg. - 6}
36 / 321
When, on account of unforeseen circumstances, a mine or part as aforesaid is abandoned or discontinued before the notice has been given or when without previous intention the discontinuance extends beyond a period of four months, the notice shall be given forthwith.
37 / 321
Notice of abandonment shall be given in which form? { reg. - 6}
38 / 321
Within how many days' notice of reopening a mine by Owner, Agent or manager shall be given to CI, RI, DM? {Reg.- 7}
39 / 321
Notice of Re-Opening is mentioned in which Regulation? { Reg. - 7}
40 / 321
In which form notice of reopening shall be given? {reg. -7}
41 / 321
Within how many days, a notice to be given to CI or RI for the change in the address of owner? {reg. - 8}
42 / 321
In which form change in the address of the owner to be submitted? {reg. - 8}
43 / 321
Appointment of Agent is mentioned in which Regulation ?
44 / 321
Notice of Accident is mentioned in which Regulation ?
45 / 321
Notice of Diseases is mentioned in which Regulation? {Reg. - 10}
46 / 321
Where any person employed in a mine contracts any disease notified by the Central Government in the Official Gazette, the owner, agent or manager shall, within ______days of his being informed of the disease, send notice to proper authority?
47 / 321
The notice of diseases to be given in form ________ and to whom?
48 / 321
Notice of accident to be given within how many days?
49 / 321
For how many days, the notice of accident copy to be kept on the notice board outside mining office? {Reg.- 9}
50 / 321
Notice of accident to be given in which form? {reg. - 9}
51 / 321
In respect of every person killed or injured as above, the owner, agent or manager shall send to the Chief Inspector particulars in Form IV-B and IV-C of First Schedule, within ___ days of the occurrence or _____ days of the injured person returning to duty, as the case may be. {Reg.- 9}
52 / 321
Which one of the following is not covered int he definition of accident in regulation 9 (reg9)
53 / 321
The chairman of the mining board shall be {reg. - 11}
54 / 321
How many members will be there in the Board of Mining examination? {Reg. - 11}
55 / 321
The members of the Mining Examination Board shall have a term of{ Reg. - 11}
56 / 321
Where shall be the location of the meeting of the examination board and how many days' prior notice to be given to the members? {Reg.-11}
57 / 321
If there is urgency of a meeting of the Mining Board, then how many days' prior notice to be given to the members? { reg. - 11}
58 / 321
No business shall be transacted at a meeting of the Board unless at leat _____ members, including the Chairman, are present. (reg11)
59 / 321
How many members should be present at the Mining Board meeting? Want. (reg 11)
60 / 321
How many types of certificates are issued by the Mining Board (reg 12)
61 / 321
Notice regarding the date and place of the examinations for the Manager’s and Surveyor’s certificates shall be published, not less than ______ days prior to the date fixed by the Board for receiving applications.
62 / 321
Minimum age of a person to appear in the exam conducted by the Mining Board Should be { reg. - 15}
63 / 321
A medical certificate obtained not more than ______year prior to the date of this application for the examination under regulation 13, shall be valid, {Reg.- 15}
64 / 321
No person shall be admitted as a candidate at any examination for a First or Second Class Manager’s Certificate unless he has the practical experience of ______ and ______ years respectively{reg. - 16}
65 / 321
In the case of a candidate who has received 5[a diploma or degree in mining or mining engineering or other equivalent qualification, approved in that behalf by the Central Government, the period of experience for first class ad second class shall be _____ years and _____ years, respectively {reg. - 16}
66 / 321
If a student obtained a degree in mining engineering, then how many years' of experience he should have to appear in second class examination? {reg. - 16}
67 / 321
In the case of a candidate who has received a certificate, diploma or degree in applied geology, civil, mechanical or electrical engineering, or other equivalent qualification approved in that behalf by the Central Government, then the period of practical experience for first and second class examination shall be __________ years and __________ years, respectively. {reg. - 16}
68 / 321
For an unrestricted first-class and second class mine managers' certificate, how many years of experience do you need in UG {reg. - 16}
69 / 321
No person shall be admitted as a candidate at any examination for a Surveyor’s Certificate unless he has satisfied the Board that he has had not less than _____ year’s practical experience of surveying of a type approved by the Board {reg. - 17}
70 / 321
In case of candidate who has received a certificate, diploma or degree in mining or mining engineering, mine surveying, or civil engineering or other equivalent qualification, how many years of experience he needs for unrestricted surveyor's certificate{reg. - 17}
71 / 321
If any person wants to appear in mate or blaster exam then, he should have practical experience of how many years. {reg. - 18}
72 / 321
The practical experience for blaster's certificate shall be reduced to_________years in the case of a candidate who has received a diploma or certificate in mining subjects or other equivalent qualification after a course of at leas two years’ duration approved in that behalf by the Central Government 4[or who received has a degree in applied geology or in civil, mechanical or electrical engineering or other equivalent qualification {reg. - 18}
73 / 321
Mining engineering students to sit in the mate or blaster's exam, at least how many years of experience they should have. {reg. - 18}
74 / 321
Will the requirement of experience in metal mine can be reduced by board if someone has experience in coal?(reg 19)
75 / 321
How many years of experience someone need to appear in an engine driver's examination? {reg. - 20}
76 / 321
Fees for grant of certificate is mentioned in which regulation?
77 / 321
A person working in a country other than India and has certificate in that country, then how many years of practical training he need in Indian mines to get a manager's certificate? {reg. - 22}
78 / 321
Which regulation has mentioned the provision of Duplicate certificates?
79 / 321
To whom the certificates of mine foreman, mine mate, engine driver or the blaster will submit his certificate?(reg 27)
80 / 321
Suspension of a certificate has been mentioned in which regulation?
81 / 321
No person shall act as a manager or an official or a blaster or a winding engine man in a mine after attaining the age of 60 years unless he has obtained, within the preceding _____year, a medical certificate of fitness certifying him fit to carry out the duties prescribed for him
82 / 321
Qualification of Inspector? {reg. - 32}
83 / 321
Minimum Age of Manager ?{ Reg.- 34}
84 / 321
The owner or agent shall provide suitable residential accommodation for the manager and the undermanager or assistant manager within a distance of _____ from all mine openings{REG..- 34}
85 / 321
Can a manager work as an agent/under manager/ assistant manager in another mine? {reg. - 34}
86 / 321
No manager shall vacate his office without giving due notice in writing to the owner or agent at least ____ before the day on which he wishes to vacate his office {reg. - 34}
87 / 321
Manager's permit as per reg 5 of 34 is valid up to? {reg. - 34}
88 / 321
If more than 150 Persons are Ordinary Employed in Underground Mines and 400 Person is Employed in all, then the selected manager in that Mines should have ? {reg. - 34}
89 / 321
If ordinarily employed in a mine is 75 in underground and less than 400 in all, in that case, what certificate is needed for manager? {reg. - 34}
90 / 321
In every mine the average employment of which exceeds ________in working below ground or ________ in all in the mine, the manager shall be assisted by assistant managers and/or underground managers {Reg.- 35}
91 / 321
What will be the age of an Engineer to appoint in Mines? {reg. - 36}
92 / 321
Total HP of HEMMs in Open cast mine which calls for an engineer having diploma or degree in mechanical engineering {reg. - 36}
93 / 321
A notice of every appointment of engineer, giving the name and full particulars of the qualifications and experience of the person so appointed, shall be sent to the Regional Inspector within _____ days of such appointment {reg. - 36}
94 / 321
Age of Surveyor to appoint in Mines will not be less than _ _ _ _ _ _ ? { reg. - 38}
95 / 321
A notice of every surveyor appointment giving the name and full particulars of the qualifications of the person so appointed, shall be sent to the Regional Inspector within ________days of such appointment.{Reg.- 38)
96 / 321
Every person using a safety lamp shall take proper care of it and shall not place it within _____metre of the swing of any tool {Reg.- 41)
97 / 321
Manager shall visit under ground mine to examine at least ________ days in a week {Reg.- 44}
98 / 321
Manager shall visit in the night shift at least within how many days {reg. - 44}
99 / 321
If there is a shortage of material in the district, within how many days owner or agent shall provide it to the manager? {reg. - 44}
100 / 321
If any incident occurs in a mine, is it the responsibility of mine management to investigate it? if yes, who shall do the investigations and report shall be kept in bound paged book?
101 / 321
What shall be the frequency of checks by assistant manager or under manager?{reg. - 45}
102 / 321
Whose responsibility is this, in the case of working belowground, -Â while on duty, he will carry a tracing of the workings of such district and shall keep the tracing up-to-date {reg. - 46}
103 / 321
It is the primary responsibility of whom to see that all traveling roadways and working places in his district are made and kept secure. {Reg.- 47}
104 / 321
Who has the authority to carry explosive? {reg. - 48}
105 / 321
In mechanical ventilators, examining the machinery and observing the pressure-recorded or water gauge and the speed indicator shall be at intervals of not more than _____{Reg.-50}
106 / 321
The surveyor shall inform about the full facts when workings of the mine have approached to about ____ metres from the mine boundary, or from disused or waterlogged workings; {reg. - 52}
107 / 321
Duties of Banksmen, Bellmen, and Signal Men are mentioned in which regulation? {reg. - 55}
108 / 321
Indian Explosive Act Formed in
109 / 321
Within how many hours, persons shall inform his presence to attendance keeper after reaching duty? {Reg.- 59}
110 / 321
Every plan or section prepared or submitted shall show a scale of the plan at least _______ centimeters long and suitably subdivided{Reg.- 60}
111 / 321
On what scale, the plan for Mica Mines and Other Small Mines are made?{reg. - 60}
112 / 321
On Which Scale, the Plan For Large Opencast Mines are made ? {reg. - 60}
113 / 321
On which scale will the plans be made for other mines except large opencast or mica mines ? {reg. - 60}
114 / 321
In how many days will the Mine Plan be updated every? {reg -60}
115 / 321
In how many days will the plan be updated in Open Cast Mines?{reg. - 60}
116 / 321
Every important surface feature within the boundaries, such as railway, road, river, stream, watercourse, tank, reservoir, opencast working and building which is within _____ metres of any part of the workings measured on the horizontal plane; shall be shown in plans {reg. - 61}
117 / 321
A vertical mine section or sections showing a vertical projection of the mine workings, where a reef, vein, lode or mineral bed or deposit has an average dip of more than ___ degrees from the horizonta {reg. - 61}
118 / 321
At what intervals the surface contours shall be shown in the case of under ground and in the case where there is no under ground working? {reg. -61}
119 / 321
where different reefs, lodes, veins or mineral beds or deposits overlie or run parallel to one another, the workings or each reef, lode, vein or mineral bed or deposit shall be shown on a separate plan and/or longitudinal section or sections; so however that if two reefs, lodes, veins or mineral beds or deposits are so situated in relation to each other than the parting between workings made therein is less than _________ metres at any place, such workings shall also be shown on a combined plan and/or longitudinal section{reg. - 61}
120 / 321
The plans required to be kept shall show the workings both above and belowground of all adjacent mines which are situated within ______ metres, measured on any plane, of the boundary claimed by the owners of the mines {reg. - 61}
121 / 321
In the case of dipute, upto how many meters shall be shown on surface plan {reg. - 61}
122 / 321
The owner, agent or manager shall, on or before the ______ of every year, submit to the Chief Inspector two up-to-date copies of the plans and sections{ reg. - 62}
123 / 321
Within how many days the plans and sections of abandoned mine shall be sent CI {reg. - 62}
124 / 321
How many means of acess/egress should be there in every mine? { reg. - 68}
125 / 321
Suitable arrangements shall be made for persons to descend and ascend by each of such shafts or outlets. Where the shaft is vertical and more than _______metres in depth, such arrangements shall be by means of a proper winding engine. { reg. - 68}
126 / 321
The shafts, inclines or outlets shall not be less than _______metres distant from one another at any point{reg. - 68}
127 / 321
The Hight of Traveling Roadway will be? { reg. - 68}
128 / 321
What will be the width of the traveling roadway? { reg. - 68}
129 / 321
if the single outlet is an un-walkable shaft (other than a shaft in the course of being sunk) and exceeds _______metres in depth, it shall be provided both with ladders and with other means of raising an lowering persons { reg. 68}
130 / 321
Mine foreman or other competent persons shall examine the shafts or other outlets at what intervals?{ reg. - 72}
131 / 321
Permanent Lining in Shaft and Winze shall be considered for what depth?{ reg. - 69}
132 / 321
Every shaft or winze, including shaft or winze in the course of being sunk, which has an inclination exceeding ______ degrees from the horizontal, shall be provided with a ladderway from the top to the bottom
133 / 321
In the case of a shaft or winze in the course of being sunk, the ladderway may be provided within such distance, not exceeding _______ metres, from the bottom as to secure it from danger during blasting operations and a chain or rope ladder shall be provided from this point to the bottom of the shaft or winze
134 / 321
Every ladder used in a mine shall be strong enough and be securely fixed in the shaft, winze or stope at an inclination of not more than ______ degrees from the horizontal
135 / 321
Where the inclination of ladderways is more than 60 degrees from the horizontal, the platforms or sollars shall be provided at intervals of not more than _____ metres. { Reg.- 75}
136 / 321
If a ladderway provided exceeds 20 metres in depth and has an inclination of more than 30 degrees with the horizontal, platforms or sollars shall be provided at intervals of not ore than ________ metres along the underlie or slope of the shaft or winze.{ reg. - 75}
137 / 321
Before installation of new winding engine, the O/A/M shall give notice to RI before how many days? {Reg. - 79}
138 / 321
At every mine where a shaft or winze is used for lowering or raising persons, at least ________ spare winding rope, suitable for use in such shaft or winze shall be kept in reserve { reg. - 81}
139 / 321
The Permissible angle of subtent in either direction of winding engine rope in relation to the head gear is? { reg. - 80}
140 / 321
The diameter of the drums or sheaves of the winding engine, and of the pulleys and sheaves used in connection with the winding shall be not less than ________ times of the dia of the rope?
141 / 321
Winding Engine Driver should have the following certificate? { reg. - 78}
142 / 321
There shall be provided one or more brakes on the drum of winding engine for the purpose of ?{ Reg. - 82}
143 / 321
What is not correct regarding the code Of Signal for winding engines in Shaft, Winze etc ? { Reg. - 83}
144 / 321
Where the shaft or winze is vertical and exceeds __________metres in depth, it shall be provided with sufficient number of guides to ensure smooth and safe travel of the cage or other means of conveyance{reg. - 83}
145 / 321
Where the shaft or winze is vertical, the gap, both vertical and horizontal, between the protective roofing and the top of cage, when the cage is at the bottom of the shaft, shall not exceed _____ . { reg. - 83}
146 / 321
At what depth of Shaft, provision for speed indicator has been mentioned in regulation 84 of MMR 1961 {reg. - 84
147 / 321
If the shaft or winze exceeds _________metres in depth, there shall be a clear over-run space of not less than _______ metres below the lowest landing place. {reg. - 84}
148 / 321
In case of every shaft or winze exceeding ________ metres in depth, there shall be provded an effective automatic contrivance to prevent overspeeding and overwinding {reg. - 84}
149 / 321
Except where an Automatic Contrivance is provided to prevent overwinding, a point shall be fixed and marked on the indicator of the engine in such a way as to show when the cage or other means of conveyance is at a distance of not less than twice the circumference of the drum from the completion of the wind; and if such cage or other means of conveyance contains persons, the winding engineman shall not, as soon as it has reached the point aforesaid, raise it for the remaining distance at a speed exceeding ________ metres per second{ Reg. - 84}
150 / 321
Tests of every Automatic Contrivance and every brake shall be made once at least in every ______ days, by raising each cage or other means of conveyance, in turn, to pass the last control point above the topmost landing {Reg.- 84}
151 / 321
The Automatic Contrivance shall prevent the descending cage from being landing at the pit bottom or other permanent landing at a speed exceeding__________ per second {reg. - 84}
152 / 321
at any one time in any cage or other means of conveyance shall not exceed _____% of the maximum load { reg. - 84}
153 / 321
Provisions for Detaching Hook shall be at what depth of shaft? {reg. - 87}
154 / 321
When the bucket or other means of conveyance is at the top landing, there shall be a clear over-run space of ? {reg. - 87}
155 / 321
When shaft sinking is in progress, overhead protection on each bucket shall be provided and sufficient number of guides shall be kept extended up to how many meters? {reg. - 87}
156 / 321
The Signaling Apparatus shall be checked or examined at an interval of ? { reg. -88}
157 / 321
Before Winding Engine Installation in Mines, O/A/M, from whom will take the permission? {Reg. - 88}
158 / 321
The gap between the floor of cage or other means of conveyance and the lowest part of the gate of fence does not exceed _______ centimetres and that between any two members of the gate or fence does not exceed __________centimetres {reg. - 88}
159 / 321
Beyond what depth of a shaft, the rope shall be made up of cold-drawn steel wire? { reg. - 88}
160 / 321
The factor of Safety of Winding Rope In Shaft Less Than 300 Meter Deep will be? {Reg- 88}
161 / 321
Exceeding 300 Meter but Not Exceeding 500 Meter in Depth Of Shaft, Winding Rope's Factor Of Safety shall be? {Reg.- 88}
162 / 321
If the Depth of the shaft Exceeds 500 Meters but Not Exceeding 700, What shall be the FOS of the Winding Rope ? {reg. - 88}
163 / 321
In the Winding Shaft, if the depth of the shaft is more than 700 Meter, but not more than 1000 Meter, the FOS of Winding Rope will be? {reg. - 88}
164 / 321
What will be the FOS of the Winding Rope in a shaft deeper than 1500 Meter? {reg. - 88}
165 / 321
What shall be the FOS of rope in case of the Winding Shaft having a depth more than 1000 Meters but less than 1500 Meter ? {reg. - 88}
166 / 321
Upto how many years an winding rope can be used in raising and lowering purpose?
167 / 321
If white metal is used in the capping of ropes, up to how much temperature the socket shall be heated before the white metal is poured into it?
168 / 321
If white metal is used in the capping of ropes, the melting Point Temperature of White Metal shall not exceed?
169 / 321
At what interval, all the parts of suspension gear shall be renewed? {reg. - 89}
170 / 321
Who can give permission to use suspension gear after 10 years {reg. - 89}
171 / 321
Every detaching bell or plate used in connection a safety-hook shall be examined, and the opening therein checked by calipers or gauges, once at least in every ______days {reg. - 89}
172 / 321
After every installation or recapping of a rope and after every renewal or refitting of any suspension gear, the engineer shall have made ______ trips up and down the working portion of the shaft, and examine the Cappel to see that they are in proper working order. { reg. - 90}
173 / 321
It's the responsibility of the engineer to check the winding equipment Once at least in every _______hours {reg. - 91}
174 / 321
Each winding rope, by passing the rope at a speed not exceeding one meter per second shall be checked by engineer at what interval?
175 / 321
Once at least in every 30 days, every winding rope, by passing the rope at a speed not exceeding _____ metre per second
176 / 321
At what interval the internal part of the Winding Engine shall be checked?
177 / 321
After each examination of the Winding Engine, who shall sign the examination report? {reg. - 91}
178 / 321
At every landing where it is necessary for persons to pass from one side of the shaft to the other, an adequate passbye shall be provided for enabling them to do so without entering or crossing the shaft. Every passbye so provided shall be not less than __________metres high and ________metres wide, and shall be kept clear of all obstructions. {reg. - 92}
179 / 321
The distance between Stop block and Runway Switch shall not be more than ------ meter?{Regulation - 95}
180 / 321
Where haulage is effected by one or more ropes, there shall be provided and maintained, tub re-railers at intervals of not more than _______;? {reg. - 95}
181 / 321
Which is incorrect regarding the Code of Single for men & material haulage?{Regulation - 95}
182 / 321
Voltage of Electric Signal shall not exceed?
183 / 321
Telephone Signaling Circuit will be?
184 / 321
Manholes shall be provided at an interval of? (Reg-95)
185 / 321
Where the inclination of the road is less than 1In6 of the distance between manholes shall be? (Reg. - 95 )
186 / 321
Hight Of Manhole ?
187 / 321
What will be the size of a Manhole? (Reg96)
188 / 321
Every manhole shall be kept clean and clear of obstruction, and white washed both inside and for a distance of not less than ____ metres around the aperture {Regulation - 95}
189 / 321
For any changes in man hole, the mine management shall take permission from whom ?
190 / 321
The hight of the Haulage Roadway shall be?
191 / 321
At all places where tubs are coupled or uncoupled, there shall be a clear space of not less than ____metre between, the tubs and one side of the roadway.
192 / 321
The height of a traveling roadway will not be less than_______Metar? {Regulations - 96}
193 / 321
Where the inclination of travelling roadway exceeds_______ degrees from the horizontal, be provided with suitable steps or ladders; ?
194 / 321
where the inclination exceeds 60 degrees from the horizontal, be provided, in addition to the steps or ladders and rails or ropes, with suitable platforms at intervals not exceeding _____ metres measured along the slope. (Reg-96)
195 / 321
On every tub there shall be provided and maintained at each coupling end a strong buffer projecting beyond the end and so arranged that when two such tubs are in tandem, the gap between the innermost ends shall not be less than _____ centimeters
196 / 321
The state of every buffer and drawbar of every tub in use and of every safety-catch, coupling-chain and other attachment shall be examined, once in (Reg-97)
197 / 321
Two or more tubs shall not be moved by hand in close succession. Two tubs shall be deemed to be in close succession when the distance between them at any time in less than _______ metres (Reg-97)
198 / 321
In traveling roadways, if the gradient is greater than ________ then the step is made with handrail?
199 / 321
Re-capping of Haulage Rope is done in how many days?(Reg-99)
200 / 321
In how many days should the Haulage Track be checked?(Reg-101)
201 / 321
Examination of haulage engine, brake-wheel, rope, and other appliances shall be carefully done by a competent person once at least in every?(Reg-101)
202 / 321
) No locomotive shall be used where the gradient of the track exceeds _____. (Reg- 103)
203 / 321
) Wherever railway wagons are specially placed so as to afford a thoroughfare, such thoroughfare shall be not less than _____ in width (Reg-104)
204 / 321
No material shall be placed or dumped within ______metres from either side of a track of rails. (Reg-104)
205 / 321
Locomotive shall be used in mine with the permission of ? (Reg.- 103}
206 / 321
Haulage road and its every track where the haulage is effected by means of mechanical power of gravity, and every safety contrivance fitted thereon, shall be checked in every (Reg-101)
207 / 321
On every length of underground roadway in which a conveyor is installed for transporting loads over a distance exceeding ________ metres, there shall be provided and maintained effective means of transmitting signals from every point on the length of the road to the place at which the machinery working the conveyor is operated (Reg- 100)
208 / 321
No belt conveyor shall be used in a mine belowground without the permission in writing of the Chief Inspector
209 / 321
Protection at loading chutes is mentioned in which Regulations?
210 / 321
Substantial fences and gates shall be provided if any building is situated at a distance of _________m from the haulage road or tramline {Regulation - 105}
211 / 321
During open cast working in alluvial soil, if any insitu pillar is left for measurement, what shall be the height of that pillar . (Reg-106)
212 / 321
During open cast working in alluvial soil, if a pillar in insitu is left which has a height of 125m, what shall be its base?(Reg-106)
213 / 321
Height of any bench in alluvial soil shall be? {Regulations - 106}
214 / 321
What will be the side slope in Manual Open Cast Working in alluvial soil? { reg. - 106}
215 / 321
In the condition of Alluvial Soil, Morum, Gravel, Clay, Debris, permission be taken to increase the gradient from the horizontal by O/A/M from?
216 / 321
Sides, where Float Deposit, and Manually Cutting are being done horizontally, will not be more than _______?
217 / 321
In the case of hard rock and float-type rock, what shall be the maximum height of the bench?
218 / 321
In open cast working in hard rock, where the height of the bench is 7.5 metres, the minimum width of the bench, under the permission fo regional inspector, shall be at least _______ Meter?
219 / 321
No tree, loose stone or debris shall unless otherwise permitted in writing by the Chief Inspector be allowed to remain within a distance of _________ metres from the edge or side of any open cast excavation(Reg-106)
220 / 321
Power Of Inspector is mentioned in which Regulations of MMR 1961?
221 / 321
Before the commencement of work, the O/A/M shall take permission for deep hole blasting and use of HEMM in open cast, from RI and CI before how many days?
222 / 321
Without written permission from the Regional Inspector, the height of Main Drive will be not less than ______ Meter.
223 / 321
Splitting or reduction of pillar dimension in UG can be done for special purpose by O/A/M, after getting permission from RI, before how many days?
224 / 321
If Chief Inspector fond any contravention of any provisions of the Act, rules , regulations or by-laws, during his visit in a mine, in which form he shall enter all the details of contravention?{ reg. - 108A}
225 / 321
The register of contravention pointed out by the Chief inspector shall be checked by O/A/M every___ day and shall be countersigned, and a copy of that shall be kept on the notice board for _____ days {reg. - 108A}
226 / 321
Before working under the Railway Line or Roadway Building, permission shall be taken from? {reg. - 109}
227 / 321
If there is a Roadway or railway Line on the Surface, then below it how many meters of Pillar shall be left? {reg. - 109}
228 / 321
For working under railway lines within the specified distance, while taking permission from the chief inspector, how many copies of plan to be submitted?{reg. - 109}
229 / 321
Protective works in abandoned mine shall be done under the permission of? {reg. - 110}
230 / 321
No working shall be made within a distance of __________metres of the boundary of any mine? {reg. - 111}
231 / 321
In case of a disputed boundary, no working shall be made within a distance of ___________metres of the boundary claimed by the owner of an adjacent mine{reg. - 111}
232 / 321
Who can give permission to work within a distance shorter than 7.5m from the mine boundary? {reg. - 111}
233 / 321
The Chief Inspector may permit the workings of any mine or part thereof to extend within any shorter distance than 7.5 metres or may require that the said working shall not extend further than a specified distance, not exceeding __________ metres, of such boundary {reg. - 111}
234 / 321
In case of steep working, upto ________ degree from the horizontal, shall be permitted to work without seatbelt or lifeline? {reg. - 114}
235 / 321
Every place in a mine, whether belowground or in opencast working including travelling roadways and landings, where work is carried on or where persons are stationed or required to pass shall be placed under the charge of a _________ {Reg.- 116}
236 / 321
The mining mate or other competent person accompanied by such assistants as may be required shall, within ____hours before the connection of work in a shift, inspect every part of the mine or district assigned to him, in which persons have to work or pass during the shift{Reg. - 116}
237 / 321
Once at least in every _____ hours, all the road ways and working places shall be inspected by mining mate. {reg. - 116}
238 / 321
In the case of a shaft in the course of being sunk, who shall be the last person to ascend the shaft at the end of the shift {reg. - 116}
239 / 321
Where several persons are working together in any place, one of them shall be placed as in-charge. What shall be his age?{Reg.- 118}
240 / 321
No person shall carry weight on a road where the gradient is greater than _ _ _ _ _ _ Degree from the horizontal? {reg. - 118}
241 / 321
What shall be the width of a walkway or footpath where there is danger to fall from more than 1.8 m height? {reg. - 118}
242 / 321
Level steps shall be provided on walkway/footpath if the inclination is more than? {reg. - 118}
243 / 321
Where the Traveling Roadway is more than 15° Degree from Horizontal What will be the size of the step? {reg. - 118}
244 / 321
Within how many meters of mine entry should all structures be made up of Fire Proof material? {Reg.- 119}
245 / 321
No person shall light a fire or permit a fire to be lighted on the surface within a distance of ____ metres from any entrance to a mine, except by an order I writing of the manager(Reg- 119)
246 / 321
Inflammable materials, shall not be stored within a distance of ______metres from any entrance to a mine {Reg.- 119}
247 / 321
Testing of Fire Fighting Equipment i.e. - Fire Extinguisher shall be done by the Competent Person at what interval? {Reg.-121}
248 / 321
At what interval, atmospheric conditions behind the seals of an area of old workings or a fire or spontaneous heating, shall be checked?{Reg.- 123}
249 / 321
At what interval a competent person shall inspect all seals erected to isolate or control a fire or spontaneous heating belowground {Reg.- 123}.
250 / 321
A per Reg 123, During every inspection by a competent person, to ascertain the general condition of every seal erected to isolate or control a fire or spontaneous heating belowground, he shall place his signature, with date. This record shall be maintained for how many days?
251 / 321
Suitable birds or other means to detect carbon monoxide, shall be kept ready in a mine, if which regulation is applicable to that mine? (Reg- 122)
252 / 321
If in a mine 100 persons or more are ordinarily employed then water taps at what interval and what shall be the length of water hoses on those taps? {reg. - 121}
253 / 321
For fire fighting, portable water tanks fitted with hand pressure pumps shall be provided in every mine and what shall be the length of hose-pipes fitted with that ? {Reg.- 121}
254 / 321
Quantity of Dust in Mines during 8 Hours Shift, Shouldn't more than _ per cubic meter?
255 / 321
Dust should not contain more than _______% of Silica?
256 / 321
Generally, survey of Dust in Mines was done at an interval of how many days?
257 / 321
The owner, agent or manger of every mine shall, once at least every _____months, cause the air at every workplace where airborne dust is generated to be sampled and the concentration of respirable dust therein determined:?
258 / 321
Every device used for the prevention and suppression of dust produced by any machinery, equipment or process as also for the filtering of the exhausted air and every dust respirator shall be inspected once at least in every _____days and shall be thoroughly examined and tested at least once in every period of _____ months
259 / 321
No plant for the screening or sorting of minerals or ores and as far as practicable, no heap of cinder, cement, sand, mortar or other dry and fine material shall be placed within _____ m. of the top of any down -cast shaft or other intake airway not shall any such material be so handled as to make it air-borne an drawn into such shaft or airway.
260 / 321
How many days before commencement of work, O/A/M shall give notice to CI, that is intended or proposed to reopen a mine or part thereof, which has been isolated, sealed off, or flooded with water to deal with a fire or spontaneous heating
261 / 321
For the precautions againt irruption of gas- Where any working is extended to within how many meters of any stoped-out area likely to contain an accumulation of inflammable/ noxious gases, there shall be maintained at least one bore-hole not less than 1.5 metres in advance of the working. (Reg - 125)
262 / 321
No working which has approached within a distance of ______metres of any disused or abandoned workings, shall be extended further except with the prior permission in writing of the Chief Inspector(Reg - 128)
263 / 321
When the owner, agent or manager intends or proposes for an intentional flooding,  he shall give in writing not less than _______ days’ notice of such intention or proposal to the Chief Inspector
264 / 321
After giving the notice to CI, for intentional flooding, by O/A/M, if that is not done within ______ days, then it shall be considered as lapsed and re-notice has to be given
265 / 321
Before the construction of a dam, how many days before, the notice shall be given to RI, and if the dam was already constructed then within how many days, the notice shall be given? (Reg-130)
266 / 321
Where to put Fire Extinguishers in a mine as per the provisions of MMR 1961?
267 / 321
The oxygen percentage in Underground Mines should not be less than? {Reg.- 131}
268 / 321
Permissible Limit Of Carbon Monoxide? {Reg.- 131}
269 / 321
Methan gas in general body of air - (CH4) should not be more than _______Â {Reg.- 131}
270 / 321
Mines in which Main Mechanical Ventilator is used, Air Measurement should be done with an interval of how many days? {reg. - 132}
271 / 321
At every shaft or winze ordinarily used for lowering or raising of persons or material, where a mechanical ventilator is installed, there shall be provided a properly constructed _______.
272 / 321
Every stopping between the main intake and main return airways shall be constructed of masonry or brickwork, not less than________centimetres in thickness
273 / 321
In every mine in which a mechanical ventilator is in use, the quantity of air circulating in every ventilating district shall be measure once at least in every ______Â days and recorded in a bound paged book kept for the purpose
274 / 321
Every auxiliary fan shall have an air-duct for conducting the air to or from the face or blind end; and such air-duct shall be so maintained as to minimise any leakage or air and to ensure an adequate supply of air to within _________metres of the face or blind end
275 / 321
The first inspection of a mine or part which is re-opened after a discontinuance of mining operations for a period exceeding ____ days and of any part of amine after being de-watered
276 / 321
CH4 [ Methane Gas] in General body of Air Quantity should not exceed____%? {reg. - 141}
277 / 321
In any part of a mine to which regulations 123(1) and 142 apply, or where the Regional Inspector may require by an order in writing, all unused workings which have not been sealed off, shall once at least in every seven days be inspected by a competent person for the presence of inflammable or noxious gas
278 / 321
In every mine having workings belowground extending to a depth of more than ____ metres from the surface, determinations shall, once at lest in every 30 days be made of temperature, humidity and such other environmental conditions as the Regional Inspector may by an order in writing stipulate {reg. - 144}
279 / 321
In which case the ventilation officer be appointed?
280 / 321
Where Lighting arrangement should be donr? {reg. - 146}
281 / 321
Adequate general lighting arrangements shall be provided during working hours in every travelling roadway normally used by _______ or more persons during any shift
282 / 321
Standard of Lighting is mentioned in Which Regulation ?
283 / 321
By Manager Assistant Manager, Underground Manager within how many days, will the Flame Safety Lamp be checked once? {reg. - 149}
284 / 321
Precaution to be Taken for Flame Safety Lamp is mentioned in Which Regulation?
285 / 321
When was the Indian Explosive Act made?
286 / 321
According to the Indian Explosive Act 1884, Explosive will be kept in? {reg. - 154}
287 / 321
No case or container shall contain more than _______ kilogrammes or explosives, and no person shall have in his possession at one time in any place more than one such case or container {reg. - 157}
288 / 321
Where explosive can be stored except magazines? {reg. - 159}
289 / 321
The maximum number of holes that can be blasted by the blaster at a time? {reg. - 160}
290 / 321
No drill shall be used for drilling a shothole unless it allows a clearance of at least _________ centimetre over the diameter of the cartridge of explosive which it is intended to use (reg162)
291 / 321
No shothole shall be fired by a fuse less than ____ metres in length
292 / 321
No person shall re-enter or be permitted to re-enter the place of blasting until __________minutes after the firing of shots
293 / 321
If any hole is blasted electrically, after how much time, a person can enter into the face after the source of electricity disconnects from the cable?
294 / 321
At what distance a relieving hole shall be drilled if any misfire happens in any hole? {reg. - 167}
295 / 321
Before the commencement of drilling in any working place, the competent person in charge of the place shall see that all looser rock is removed from the face and the area lying within a radius of _________metres of the proposed shothole is thoroughly cleaned or washed down with water and carefully examined for the presence of misfires or sockets
296 / 321
No more than ____holes shall be fired in one round unless they are fired electrically or by means of an igniter cord
297 / 321
At what interval, electrical shotfiring apparatus shall be cleaned and thoroughly overhauled by a competent person? {reg. - 163}
298 / 321
The blaster shall use a well-insulated cable of sufficient length to permit him to take proper shelter, and in no case, shall this cable be less than ________meters in length {reg. - 163}
299 / 321
Danger Zone in blasting, Means ? {Reg. - 16}
300 / 321
In the case of an opencast working, where any permanent building or structure of permanent nature, not belonging to the owner, lies within the danger zone, the aggregate maximum charge in all the holes fired at one time shall not exceed _____________kilograms
301 / 321
Immediately before charging a shothole or a round of shotholes, and again before firing the shots, the blaster shall carefully test for inflammable gas at all places within a radius of ______ metres of the place of firing.
302 / 321
No internal combustion engine or steam boiler shall be used belowground in a mine expect with the permission in writing of the ___________ {Reg.- 171}
303 / 321
Air Receiver of pressurized apparatus will be tested once in how many days? {reg. -173}
304 / 321
A competent person or persons appointed for the purpose of examining machinery, once at least in every ______days, make a thorough inspection of all machinery and plant in use {Reg.- 176}
305 / 321
Fencing installed on the surface should be checked in? {reg. - 177}
306 / 321
Calcium carbide shall not be taken or kept belowground until about to be used, except in a secure metal case or container containing not more than _______ gram in weight{Reg.- 179}
307 / 321
Protective Footwear (Safety shoes) will be given free in an interval of how many days? {reg. - 182}
308 / 321
Helmet shall be given to the person working in mines in the interval of how many days? {Reg. - 182A)
309 / 321
Manpower Distribution Plan is made in? {Reg.- 184}
310 / 321
In Which of the Following Cases , Place of Accident Not be Disturbed ? {Reg.- 190}
311 / 321
In Mine if an Accident place is not inspected by the by Chief Inspector/Regional inspector/inspector within a time of _ _ _ _ _ _ then work can be started again at that place?
312 / 321
Before MMR1961, which MMR was being being followed? {Reg.- 196}
313 / 321
If an order made by RI is not acceptable or the mine management thinks is not fit for them, within how many days they can appeal to CI? (Reg.- 194}
314 / 321
In the casse of Appeals to teh mining boards or central govt, against any order of the Chief Inspector an appeal shall lie, within _____days of the receipt of the order by the appellant, to the Committee constituted under section 12 {Reg.- 195}
315 / 321
Notice of Opening / Re - opening / to change ownership is applied in which form ?
316 / 321
In which form is the Quarterly Return filled?
317 / 321
Annual Return for the Year ending on the 31 December is filled in Which form?
318 / 321
Notice of Accident is filled and sent to DGMS in Which Form ?
319 / 321
Particulars of Deceased/ Injured Person Details to be given within 7 days of the incident, in which form?
320 / 321
Particulars of Injured Person Returned to duty To be Separately given, in Respect of Every Person, Within 15 Days of his Return to duty, in Which form ?
321 / 321
Notice of Diseases Notified Under Section 25 shall be given in which form ?
The average score is 0%
Mines Vocational Training Rules - 1966
1 / 111
Category: The Vocational training rule 1966
1.
2 / 111
2.
3 / 111
3.
4 / 111
4.
5 / 111
5.
6 / 111
6. Training under MVTR 1966 Shall Not be Applied to The Following Person?
7 / 111
7.
Person prior to deployment on Surface or in Opencast Mines, According to which schedule training is given?
8 / 111
8.
9 / 111
9.
10 / 111
10.
11 / 111
11. As Per 3rd Schedule of V. T. Rules 1966, Additional Training For Entrants to Gassy Mines Shall be Given For---------------------------- Day ?
12 / 111
12. Every person who is already employed in Mines on Surface or Open Cast will be given training as per which schedule before joining Gassy Mines?
13 / 111
13. According to which schedule training is given to the person working in Underground Mines before employment in Gassy Mines?
14 / 111
14. If a person working in Mines remains absent for 1 year or more, after that he returns to Mines, then according to which schedule training will be given to that person?
15 / 111
15.
16 / 111
16. How many lectures will be given as training to the person working in Gassy Mine ?
17 / 111
17. According to which schedule, training will be given to the already employed person in Mines?
18 / 111
18. According to 4th schedule extra training will be given to the person working in _________ degree mines?
19 / 111
19. According to which schedule training will be given to Timbermen Mistry?
20 / 111
20. The person working as a Shot-Firer has been absent for 6 months or more. When he or she returns to work, according to which schedule will he or she be given training?
21 / 111
21. According to which schedule training will be given to the person working in the post of ShotFirer?
22 / 111
22. According to Schedule 6th, how many lectures of training will be given to the person working in Open Cast Metal Mines?
23 / 111
23. Before giving exam to Shotfirer / Blaster {within 3 months} a ​​Person will be given training according to which schedule ?
24 / 111
24. If a person is appointed as Blaster/Shotfirer, within how many days - training will be given to the person as per 7th schedule?
25 / 111
25.
26 / 111
26. Shotfirer engaged in the work of Explosive carrying will be given training as per which schedule?
27 / 111
27. The person already working in Explosive Carrying will be given Re-Fresher Training as per Schedule 13 within how many days?
28 / 111
28. Who will be responsible for the Management & maintenance of the training center?
29 / 111
29. Group Training Center can be made on the written permission of C.I.M {Chief Inspector of Mines}?
30 / 111
30. Without the written permission of the C.I.M {Chief Inspector of Mines} the Manager can not handle the post of Training Officer for ____ days.
31 / 111
31. At the interval of ___ days, the Training Officer will give his report to the Agent, Manager, Owner and Chief Inspector of Mines ?
32 / 111
32. Will the Trainers be given Training Allowance?
33 / 111
33. If a person remains absent in Mines for 1 year or more, then after returning to work, how many hours of lectures will be given?
34 / 111
34. At least how many days of Practical Training {Lamp Handling} will be given to the person before appearing in the Gas Testing Exam?
35 / 111
35. In which form- the certificate will be issued after training, to the person working in Non Gassy Mines, Surface or in Open Cast Mines ?
36 / 111
36. After retraining for Special Department, in which form the certificate is issued ?
37 / 111
37.
Notice of Training Program as per Schedule XII is kept in which form ?
38 / 111
38. Certificate of Training for Employment in a Mine Surface /Opencast Mine / Below Ground In Non - Gassy Mine is given in which Form ?
39 / 111
39. In which form- Certificate Of Re- Fresher Training / Training Of Special Categories Of Workmen is given ?
40 / 111
40. In which form- the record for Notice Of Opening/Close/Re - Opening/Charge Of Training Center is kept as per Schedule XII ?
41 / 111
41.
42 / 111
42. In which form the record of performance of a person undergoing training, is kept ?
43 / 111
43. In which Form the record of Performance of Trainee is kept?
44 / 111
44. According to Schedule XII, how many days Basic Training will be given to Track Layers (Line Mistry)?
45 / 111
45. How many days of Re-Fresher Training is given to Track Layers (Line Mistry) as per Schedule XII?
46 / 111
46. Persons working in Ventilation Bratice Gang, how many days of refresher training will be given to the person ?
47 / 111
47. How many days of basic training will be given to the Ventilation Brattice Gang?
48 / 111
48. How many days Basic Training will be given to the person working as attendants Of Fan Including Auxillary Fan ?
49 / 111
49. How many days Fresher Training will be given to the person working as attendants Of Fan (Pankha Khalasi) Including Auxillary Fan?
50 / 111
50. How many days of total training will be given to General Labor (ordinary laborer) ?
51 / 111
51. How many days of total re-fresher training will be given to General Labor (ordinary laborer) ?
52 / 111
52. How many days of basic training is given to Tyndals Employed [heavy weight lifting]?
53 / 111
53. How many days of refresher training is given to Tyndals [lifting heavy goods] ?
54 / 111
54. How many days of training will be given to the Person Employed On Installation, Repair And Maintance Of Machine [Mine repair worker ] ?
55 / 111
55. How many days of refresher training is given to the Person Employed On Installation Repair And Maintance Of Re-Fresher to Machine [Mine Repair & Maintenance]?
56 / 111
56. How many days basic training will be given to the person working in Coal Cutting / Drilling Machine Crew ?
57 / 111
57. How many days of refresher training is given to the person working in Coal Cutting / Drilling Machine Crew ?
58 / 111
58. For how many days basic training is given to the person working as Attandant of Haulage and Conveyor ?
59 / 111
59. How many days of Re-Fresher Training is given to the person working as Attandant Of Haulage and Conveyor ?
60 / 111
60. According to the Mine Vocation Training Rules, 1966, at least how many days of Re-Fresher Training will be given to the person working in Mines ?
61 / 111
61. According to MVTR 1966, at least how many days of basic training will be given to a worker in Mines ?
62 / 111
62. At least how many days basic training will be given to the person working in Stowing Gang ?
63 / 111
63. How many days Refresher training will be given to the person working in Stowing Gang?
64 / 111
64. For how many days basic training will be given to the person engaged in the work of Cleaning / Stone Dust Barrier ?
65 / 111
65. How many days of Re-Fresher Training will be given to the people engaged in the work of Cleaning / Stone Dust ?
66 / 111
66. How many days of basic training is given to the person before he is engaged in the work of Pick Miner ?
67 / 111
67. How many days of Re-Fresher Training is given to the people engaged in the work of Pick Miner ?
68 / 111
68. For how many days the person doing the work of Trammer is given Basic training ?
69 / 111
69. For how many days Refresher Training is given to Trammer ?
70 / 111
70. How many days of basic training is given before the loader is put to work ?
71 / 111
71. Person doing the work of Loading activity will be given how many days of Re- Fresher Training ?
72 / 111
72. Crane Operator { Including Mobile Craine Operator}- how many days of Basic Training is given to the Person?
73 / 111
73. Crane Operator { Including Mobile Craine Operator}- how many days of Re-Fresher Training is given to the Person?
74 / 111
74. How many days of Basic Training are given to Drill Operators before they are employed?
75 / 111
75. How many days of Re-Fresher Training will be given to Drill Operators ?
76 / 111
76. How many days Re - Fresher Training is given to Engine Drivers ( Loco Drivers)?
77 / 111
77. How many days of basic training is given to Loco Drivers before they are employed ?
78 / 111
78. How many days of Basic Training are given to Dozer Operators before they are employed ?
79 / 111
79. How many days of Re-Fresher Training is given to Dozer Operators ?
80 / 111
80. How many days of Basic training is given to the Loader Operator before he is put to work ?
81 / 111
81. How many days of Re-Fresher Training is given to Dozer/ Loader Operator ?
82 / 111
82. How many days of Basic Training is given before employing Dumper Operator ?
83 / 111
83. How many days of Re-Fresher Training is given to Dumper Operator ?
84 / 111
84. How many days of Basic Training is given to Shovel Operator before running a Shovel ?
85 / 111
85. For how many days Re-Fresher Training is given to Shovel Operator ?
86 / 111
86. How many days of basic training is given to the person working in the Person Employed in Store Room ?
87 / 111
87. How many days of Re-Fresher Training is given to the person working in the Material Store Room ?
88 / 111
88. How many days of Basic Training is given to a person before employing him in Welding and Gas Cutting work ?
89 / 111
89. How many days of Re-Fresher Training is given to the person working in Welding/ Gas Cutting work ?
90 / 111
90. How many days of basic training is given to the person before employing him as a Fitter Helper?
91 / 111
91. How many days of Re - Fresher Training is given to the person who works as Fitter Helper ?
92 / 111
92. How many days of Basic Training is given to the Person before employing him as a Fitter- Electrical ?
93 / 111
93. How many days of Re-Fresher Training is given to the person working as Fitter-Electrical, Electrician ?
94 / 111
94. According to MVTR 1966, the Vocational Training (VT) of a person is given for how many days ?
95 / 111
95. According to MVTR 1966, for how many days first-aid training is given to the person ?
96 / 111
96. (96.) According to MVTR 1966, for how many days the training of Gas Testing {Lamp Handling} is given as per Schedule F ?
97 / 111
97. For how many days- Class Room Induction Training is given as per Schedule - D ?
98 / 111
98. (98.) Total Training Day Available In Rule - 1966 ?
99 / 111
99. According to Schedule H- for how many days should the Job Training be ?
100 / 111
100. (100.) Minimum Qualification Of Mining Sardar & Surveyors?
101 / 111
101. What shall be the qualification of Training Officer ?
102 / 111
102. Training Officer must have at least how many years of experience in mining?
103 / 111
103. The instructor should have at least which certificate of competency?
104 / 111
104. Training Supervisor should have the following certificate?
105 / 111
105. Vocational Training (V.T) is given to the person working in Mines at the interval of how many days?
106 / 111
106. The person working in Mines will be given Re-Fresher Training in the gap of how many days?
107 / 111
107. Shotfirer, Mining Sardar, Overmen, Support Men, Machine Operator should be given the training of "Gas Testing" in how many days?
108 / 111
108. In a slot, how many people together can be given a training in Vocational Training Center (VTC)?
109 / 111
109. How much salary should be given to the person doing VTC training ?
110 / 111
110. What should be the age of an Instructor Training Officer?
111 / 111
111. (111.) Full Form ?
T.O = Training Officer
VTC = Vocational Training Center
CIM = Chief Inspector Of Mines
DMS = Director Of Mines Safety
RIM = Regional Inspector Of Mines
DGMS = Director General Of Mines Safety
Welcome to Mine Crenche Rules 1966 MCQ Questions
1 / 24
2 / 24
3 / 24
4 / 24
5 / 24
6 / 24
7 / 24
8 / 24
9 / 24
10 / 24
11 / 24
12 / 24
13 / 24
14 / 24
15 / 24
16 / 24
17 / 24
18 / 24
19 / 24
20 / 24
21 / 24
22 / 24
23 / 24
24 / 24
Welcome to Central Electricity Authority {CEA - 2010} Mine Electricity Rules 2010 MCQs
1 / 240
(1.) Full Form Of CEA ?
2 / 240
(2.) Before the year 2003, which Electricity Act was used to exchange electricity in India?
3 / 240
(3.) When were the Indian Electricity Acts first made in India?
4 / 240
(4.) When did the Indian Electricity Rules 2010 come into force in India?
5 / 240
(5.) Low Voltage Means ?
6 / 240
( 6.) Medium Voltage Means ?
7 / 240
(7.) High Voltage Means ?
8 / 240
(8.) Extra High Voltage Means ?
9 / 240
(9.) Write 6600 Volt in KV?
10 / 240
(10.) Can Electricity be carried on Underground Mines, Open Cast Mine, Mine Surface till Boundary?
11 / 240
(11.) Underground Mine, Open Cast Mine, How much Electricity can be taken out of 11 KV Electric which is carried on Mine Surface?
12 / 240
(12.) Hand Held Apparatus such as - Maximum Voltage up to what maximum current can be used in Coal Drill Machine?
13 / 240
(13.)What is the maximum number of Volts Electricity can be used up to in Underground Mine for Lighting?
14 / 240
(14.) Electric can be used up to what voltage for maximum lighting in Open Cast Mine?
15 / 240
(15.) What is the maximum Volt in Hand Held Portable Apparatus, Remote Control, Interlock Circuit till Electricity Can Be Used?
16 / 240
(16.) Electricity is brought from the Electric Company to the Central Sub-station of Mines through the Overhead-Line to the Maximum Voltage up to what?
17 / 240
(17.) From the Central Sub-Station to the Mine, up to how many Voltage Electricity can be supplied ?
18 / 240
(18.) How Much Voltage for Main Fan, Winding Engine, Sump Motor, Main Pump in Big Mine Till current is needed?
19 / 240
(19.) L.H.D. , S.D.L. How much voltage current is required to run a big machine?
20 / 240
(20.) How much Volt Current is required to run Contineous Miner?
21 / 240
(21.) How much voltage current does Drgline, Shovel, Drill machine operate in Large Open Cast Mine needs ?
22 / 240
(22.) Maximum how many sub station are available in Large open cast mine?
23 / 240
(23.) Up to what maximum voltage current is used in the pump?
24 / 240
(24.) By which machine 550 volts is converted into 125 Volt to give Electric Supply in Drill Machine?
25 / 240
(25.) What type of Apparatus is Auxillary Fan?
26 / 240
(26.) What are the Apparatus which reduce permanently in one place, what are they called?
27 / 240
(27.) Such Electric Apparatus which can walk while in operation are called?
28 / 240
(28.) Such Electric Apparatus which do the work in a steady state, but they are easily available when needed. They can be taken from one place to another place are called ?
29 / 240
(29.) Apparatus used by holding in hand is called?
30 / 240
(30.) Portable Apparatus like CCM, LHD, SDL, how many cores are there in Traillng Cable ?
31 / 240
(31.) Metal screen plating on the core of the cable is called?
32 / 240
(32.) Such a device which automatically cuts off the current when the current in the conductor is high is called?
33 / 240
(33.) Hand-operated device by which the connection of the circuit can be opened or closed can be done is called ?
34 / 240
(34.) Such a switch which is made to cut or connect all the poles of the circuit together, is called?
35 / 240
(35.) By which Apparatus the Voltage is reduced to give Electric Current in the face-mounted machine like (SDL, LHD, CM Rood Header) in Mine?
36 / 240
(36.) Full Form of Circuit Breaker ?
37 / 240
(37.) Which type of circuit breaker is used in voltage above 3.3 KV or 33 KV?
38 / 240
(38.) Such Switchgear which is used to cut off the supply of the section is called?
39 / 240
(39.) When many Switchgear are put together at one place, they are called?
40 / 240
(40.) A conducting wire, cable, pipe, plate from which electricity flows is called?
41 / 240
(41.) The Electrical Supervisor should have the following certificate?
42 / 240
(42.) At least how many years of experience the Electrical Safety Officer employed in Mine should have?
43 / 240
(43.) In which form will the Electrical Safety Officer will keep the recode of his investigation?
44 / 240
(44.) Agent, Manager, Owner in Mine having Connected Electrical Load more than ___ KW Will appoint an Electrical Safety Officer?
45 / 240
(45.) Will Danger Notice be imposed in for the Installation Overhead Line Electric Plant exceeding _______ Volt?
46 / 240
(46.)Â Will the Earthing System be installed and placed in a place with more current supply than ____ Volt?
47 / 240
(47.) Inspection of Electric Installation or Apparatus in Mines should be checked in the interval of how many days?
48 / 240
(48.) Electrical installation should be checked by the Inspector after an interval of how many years?
49 / 240
(49.) At least how many gas masks should be there to deal with fire and water in mine?
50 / 240
(50.) In how many days should the non-extinguishing equipment (Sand filled bucket, fire extinguisher) be checked?
51 / 240
(51.) When the Transformer Capacity is _____ MVA, the Protectine Equipment will be kept in that Mines?
52 / 240
(52.) If a person dies due to electrical shock then the manager will give his information to the Inspector within what time duration ?
53 / 240
(53.) If a person dies or is likely to die due to an Electrical Accident, then the Manager Within how much time will give its written report to Inspector ?
54 / 240
(54.) Installation of more than - - - - - - - Volt of Electric Supplier will be done by the Inspecting & Testing Inspector in a span of 5 years?
55 / 240
(55.) Electrician or other Competent Person working on Overhead Une will be given the following Safety Device?
56 / 240
(56.) If leakage is found in the installation of the consumer, then the Electric Supplier Inspector after how much time will disconnect the power supply after getting the permission?
57 / 240
(57.) Circuit Breaker in Current up to --------Voltage for Large Transformer or Equipment Will it be imposed?
58 / 240
(58.) How long before the consumer will be given notice to shut down for Switching Electric Supply for Testing Maintenance & Planned Work ?
59 / 240
(59.) What should be the minimum Voltage Installation Resistance of more than 650 Volts in Mines?
60 / 240
(60.) What should be the minimum installation resistance of equipment up to 650 Volt in Mines?
61 / 240
(61.) What should be the minimum installation resistance in a 33 KV sub-station?
62 / 240
(62.) What will be the clearances for each switch board in the installation above 250V?
63 / 240
(63.) In the earthing system of the Electric Supply Company, the resistance testing should be done in the interval of how many days?
64 / 240
(64.) An Earth Leakage Protective Device will be Installation to the Electric Supply what should be the current so that the current can be cut off immediately?
65 / 240
(65.) After testing the resistance in the Earthing System of the Electric Supply Company, that record will be kept safe for at least how many days?
66 / 240
(66.) From whom permission is taken before electrical installation above 650V?
67 / 240
(67.) Before electrical installation of more than 650V or before making changes to whom will the record be sent?
68 / 240
(68.) The following arrangements will be made near Oil Apparatus more than 2000 Liters?
69 / 240
(69.) For transformers with 10 MVA or larger or more than 2000 Liters for Oil Transformers how will the Type Protection System be installed?
70 / 240
(70.) The following protection will be taken during the power supply of more than 650V?
71 / 240
(71.) According to which code the Electric Supply, Installation Cable, Supply Line of more than 650V will be tested ?
72 / 240
(72.) Except Overhead Line Metallic Sheeted to Other Conductor of more than _______ Volt Will it be done?
73 / 240
(73.) Every supplier and consumer must test the Earthing System once in an interval of how many days?
74 / 240
(74.) In which season will the Earthing System be tested every year?
75 / 240
(75.) Will the Earthing System of the Neutral Point of each Generator, Transformer be connected separately?
76 / 240
(76.) At least how many meters high Fencing will be installed around the Outdoor Sub-Station?
77 / 240
(77.) Will the arrangement of Adequate Ventilation be done in the Sub-Station/ Switch Station?(
78 / 240
(78.) From whom to get permission if the height is to be increased than the Contractor for Below Overhead Line, Road, Building, Embankment, etc. ?
79 / 240
(79.) Any sub-station limit or 650 Volt blasting is to be done within 300 meters of the supply or tower, then permission will be taken from whom?
80 / 240
(80.) If the Voltage at Overhead Line is 650 Volt or less than the distance between the supports will not be more than  _____ meter?
81 / 240
(81.) If the telecommunication line is placed on the pole through which the power line is passing, then the breaking strength of the conductor of the telecommunication line will not be less than how many Kg?
82 / 240
(82.) Breaking Strength of Guard Wire will not be less than?
83 / 240
(83.) At how many points will each wire of the overhead line be placed in 1 kilometer?
84 / 240
(84.) Every Stay Wire shall be earthed, insulator at least up to the _____Meter?
85 / 240
(85.) Two Overhead Power Line One Ten Meter will not be less than ______ Meter?
86 / 240
(86.) To get supply on Overhead Line what will be used for it?
87 / 240
(87.) What will be the scale made on Mines Electricity Plan be ?
88 / 240
(88.) Annual Returns of Electric Apparatus, Size, Type, Use will be sent to the Electrical Inspector of Mines by filling up to which date every year ?
89 / 240
(89.) How many places in Mines, where there can be a danger due to power outage will the Flame Safety Lamp be kept?
90 / 240
(90.) What is the maximum voltage that can be used in Fixed Apparatus with Bolted Plug?
91 / 240
(91.) Transformer Details Which Regulations ?
92 / 240
(92.) To whom will the Annual Returns of Electrical Apparatus be deposited by the Mines Manager?
93 / 240
(93.) Isolation And Fixing Of Transformer And Switch gear Which Regulation ?
94 / 240
(94.) A barbed wire will be installed in the middle of the Anti Climbing Device Pole till ______ meter, on which Will a notice board showing Voltage be installed?
95 / 240
(95.) Electric Supply System of Underground Mine shall be designed in such a way that 1100V do not exceed the fault current in the installation up to _____ ?
96 / 240
(96.) Setting of Earth Leakage Relay?
97 / 240
(97.) Switchgear installed to automatically cut off the power supply fault of the mine will be checked and recorded in the working copy of Relay after what time span?
98 / 240
(98.) What should be the Power Supply System of Mines to keep the Fault Current in Limit?
99 / 240
(99.) Restricted Neutral System of Power Supply is beneficial because ?
100 / 240
(100.) Restricted Earth Neutral Power Supply System from 1.1 KV to 11 KV in Open Cast Mine To what extent should the fault current be kept limited?
101 / 240
(101.) The effectiveness of Switch Gear and Relay should be checked at intervals of how many days?
102 / 240
(102.)What is the Maximum Voltage can be used in Fixed Apparatus with Bolted Type?
103 / 240
(103.) Where the Voltage exceeds 125, where in the opinion of the Inspector there is danger from Coal Dust or Inflammable Gas
Other Cable will not be used except the following Type Cable?
104 / 240
(104.) If the current is supplied more than 250V but up to 650V, then the distance between Metallic Covering and Earth Conductor should not exceed ?
105 / 240
(105.) The metallic cover of each cable shall be such that all the parts of the cover, each joint the conductivity will not be less than what --------% of the cable has the greatest conductivity?
106 / 240
(106.) The conductivity of each screen of the cable will not be less than the power conductivity?
107 / 240
(107.) The total conductivity of all screens will not be less than that of copper wire conductivity?
108 / 240
(108.) How Many Cores are in Portable and Transportable Apparatus Flexible Cable?
109 / 240
(109.) Type Connector in Flexible Cable for Machines from 650 Volt to 33 KV will it be imposed?
110 / 240
(110.) Length of Flexible Cable in Portable & Transportable Apparatus in Mine will be maximum?
111 / 240
(111.)Â Long Wall Machine, Shuttle Car, L.H.D. in Underground Mines. The length of the cable will not exceed the maximum by how many meters?
112 / 240
(112.) What will be the maximum length of cable for HEMM in Open Cast Mine?
113 / 240
(113.) Bucket Wheel Excavator maximum length of Trailing Cable for 11 KV, how many meter will it be?
114 / 240
(114.) What will be the maximum length of Trailing Cable of SDL Machine in Underground Mines?
115 / 240
(115.)Â Intrinsically Safe Circuit will be installed in?
116 / 240
(116.) The length of Trailing Cable in Continuous Miner will not exceed how many meter?
117 / 240
(117.) The length of the Trailing cable in the Dragline will not exceed how many Meter?
118 / 240
(118.) Flexible cable is used for?
119 / 240
(119.) From whom permission is taken to increase the length of dragline cable more than 600 meters?
120 / 240
(120.)Where will the flexible cable be connected to the main cable?
121 / 240
(121.) Voltage in Signaling will not exceed ---------------------Volt?
122 / 240
(122.) What % of Inflammable Gas (CH4) Methane Gas in Gassy Coal Seam of any degree, electricity supply will be cut off from that place if found?
123 / 240
(123.) At what distance will the FLP (Flame Proof Apparatus) be placed from the face in First Degree Mines?
124 / 240
(124.)At what distance will the FLP Apparatus be placed from the face in Second Degree Mines?
125 / 240
(125.) At what distance will FLP Apparatus Face / Goaf be placed from Last Ventilation in Third Degree Mine?
126 / 240
(126.) Intrinsically Safe Circuit Remote Control Insulator Tester Circuit, which degree of Mine will it be put in?
127 / 240
(127) What type of Apparatus Machine Approved by DGMS will be used in Underground Mines?
128 / 240
(128.) Cable to be used on Surface -------------- as per specification would you be?
129 / 240
(129.) Sub-station limit or electrical supply line of more than 650V in mine boundary Of................................................. If blasting is to be done for any work within ....... meters, then contact the concerned electrical inspector. Permission will be taken.
130 / 240
(130.) From whom permission will be taken before the use of Electric Locomotive & Battery Locotive with Trolly Wire Method up to 650V in Underground Mines?
131 / 240
(131.) Where A.C. The Voltage of Supply is more than --------------------- Volt, where the Nutral Point or Mid Point will be earthed?
132 / 240
(132.) What type of certificate should the appointed Electrical Supervisor have?
133 / 240
(133.) If any Electrical Supervisor is absent, then Owner, Agent, Manager will be appointed as Subtitute Electrical Supervisor instead of him for how many days?
134 / 240
(134.) After how many days of absence (absence) of the Electrical Supervisor, its notice will be sent to the Inspector?
135 / 240
(135.) On whose permission will the Electrical Supervisor work in more than one mines?
136 / 240
(136.) Who can give Deviation in the Indian Electricity Rules 2010?
137 / 240
(137.) The pilot circuit should not operate at a voltage lower than________ if the power comes on after being cut off while in the Pilot Switch Run Position.
138 / 240
(138.) Who writes the Daily Electrical Log-book?
139 / 240
(139.) Conductivity of each screen in a separately screened cable will not be less than that of the power core?
140 / 240
(140.) Cap Lamp is Apparatus?
141 / 240
(141.) If the Overhead OH Line crosses a public road, what will be the minimum clearance from the ground?
142 / 240
(142.) Clearance Sag,(mistake) of the lowest ground conductor?
143 / 240
(143.) What will be the minimum clearance between two conductors?
144 / 240
(144.) OH Line crosses Haul Road, then there will be a clearance of how many meter between Big Dumper & Sag (Soul) of Cable.
145 / 240
(145.) OH Line crosses a Haul Road, then there will be clearance of how many meters between Earth & Cable?
146 / 240
(146.) In intrinsically safe circuit, the voltage of the circuit does not exceed.
147 / 240
(147.) Intrinsically safe Apparatus are used in Second & 3rd Degree Mine.
148 / 240
(148.) The FLP Apparatus will be as follows -
149 / 240
(149.) External Temprature in FLP Apparatus will not exceed?
150 / 240
(150.) At what degree the temprature can cause a fire in methane gas?
151 / 240
(151.) What should be the temprature for the fire to start in the wood connected to the FLP.
151.) What should be the temprature for the fire to start in the wood connected to the FLP.
(151.) What should be the temperature for the fire to start in the wood connected to the FLP ?
152 / 240
(152.) If Current on the Overhead Line is 650 Volt or more than that then what will be the distance between the Vertical and Overhead Line from the roof of any house ?
153 / 240
(153.) Current on the Overhead Line 650 Volt. Then what will be the vertical distance between the overhead line and the ceiling?
154 / 240
(154.) If on the Overhead Line Current is 650 Volt then the distance of the cable horizontally from the terrace, balcony, will not be less than?
155 / 240
(155.) The current on the OH line is up to 650 volts, then the distance of the cable horizontally from the terrace, balcony will be?
156 / 240
(156.) If the current on the overhead line is more than 33KV, the vertical distance of the roof will be?
157 / 240
(157) The breaking strength of the conductor of the overhead line will not be less than?
158 / 240
(158.) If Overhead Line Current 650 Volt then between Street and Overhead Line distance will not be less than ?
159 / 240
(159.) If the current exceeds 650V then the distance between the OH line and the ground steel will not be less than ________ meter ?
160 / 240
(160.) Provisions of lesson ix of CEA [Central Electricity Authority] Regulation 2010?
161 / 240
(161.) Who is responsible for complying with Lesson ix of CEA Regulation 2010?
162 / 240
(162.) New Apparatus over 650 Volts to be Installed in the Mine after meeting with the Electrical Inspector of Mine, how many days before the notice will be given?
163 / 240
(163.) If the Overhead Line crosses the Dumper tlau / Road, then the lowest point of the Overhead Line is What will be the minimum height of the current Canductor from the ground?
(163.) If the Overhead Line crosses the Dumper tlau / Road, then the lowest point of the Overhead Line Conductor must be of minimum what height from the ground ?
164 / 240
(164.) How will the sub-station in the underground part of the mine be kept ?
165 / 240
(165.) All non-current carrying metal parts of the electric system shall be connected to an earthing system which wil be ?
166 / 240
(166.) The Electric Supply System of Underground Mine shall be designed in such a way that 1100V Do not exceed the fault current in the installation up to ?
167 / 240
(167.) Setting of Earth Leakage Relay?
168 / 240
(168.) Switchgear installed to automatically cut off the power supply fault of the mine and will it be checked and recorded in the working copy of Relay after how many days ?
169 / 240
(169.) What should be the Power Supply System of Mines to keep the Fault Current in Limit ?
170 / 240
(170.) Restricted Neutral System of Power Supply is beneficial because ?
171 / 240
(171.) Restricted Earth Neutral Power Supply System from 1.1 KV to 11 KV in Open Cast Mine To what extent should the fault current be kept limited ?
172 / 240
(172.) According to CEA Registration 2010, can Electricity be used at what m
(a) 550V          (b) 1100V                 (c) 3300V .      (d) 6600 V
aximum Volt in the Underground part of the mine?
173 / 240
(173.) Maximum up to how many Volt Electric can be used in Remote Control Circuit ?
174 / 240
(174.) In which underground mine of India, electricity is transmitted at 11 KV, and 3.3 KV is used ?
175 / 240
(175.) Switchgear with safety device for safety shall be installed at the proper place?
176 / 240
(176.) As per CEA (Electricity Supply Regulation2010) Cars powered by electricity to the fan Inter lock will be done with the power supply of the mine in such a way that when the main fan is off, the power will be Supply gets automatic cut to which degree of mine will this provision be applicable?
177 / 240
(177.) Open Sparking Means?
178 / 240
(178.) What does Last Ventilation Can Action Means in District?
179 / 240
(179.) Cable -
180 / 240
(180.) CEA Reg. Switchgear ________ will be arranged to supply electricity as per Reg-105 of 2010 ?
181 / 240
(181.) Auxiliary Fan in the Underground Part of Degree Gassy Seam will be kept interlocked with the Electric Supply of the Face Machine in such a way that if the Auxiliary Fan is turned off then the Electricity of the Face Machine will be automatic?
182 / 240
(182.) The Conductivity of Metal Caverin of all cables except the Flexible Cable of Portable and Transportable Apparatus of Mine shall not be less than A` on all parts or at all Joint A` means?
183 / 240
(183.) What will be the financial cover of Electric Cable?
184 / 240
(184.) According to CEA, Electric Shovel is ?
185 / 240
(185.) Electricity Reg. Flexible Cable of Any Portable & Transportable Apparatus as per the length will not be less than ______ meter?
186 / 240
(186.) National cover in Flexible Cable of Portable Apparatus more than 250 V will be ?
187 / 240
(187.) As per Electricity Rules 2010, the length of Trailing Cable of LHD and Shuttle Car shall not exceed _____ meter?
188 / 240
(188.) 250V Financial Coverage in Flexible Cable of Portable Apparatus of more than ?
189 / 240
(189.) In a flexible cable with a screen, which will not be ______ Less than the conductivity of the screen?
190 / 240
(190.) Under what conditions can On-Screen Cable be used with Portable Apparatus?
191 / 240
(191.) The plyable wire of the axillary fan is an armored cable as per the Electricity Rules 2010 should be ?
192 / 240
(192.) The length of the trailing cable of a 3.3 kv continuous miner shall not exceed ?
193 / 240
(193.) According to CEA 2010, the length of the Bucket Wheel Excavator's Flexible Cable can be kept up to how many meters?
194 / 240
(194.) Which is used in Electrical Apparatus Fix condition but can be moved from one place to ten easily in place?
195 / 240
(195.) When two conductors of a flexible cable are joined together, then their joint are kept away, Why?
196 / 240
(196.) The length of the cable of Transportable Apparatus like Axillary fan shall not exceed .................. meters?
197 / 240
(197.) The Trailing cable of the portable apparatus shall have a flexible metal screen, if the voltage exceeds ……….
198 / 240
(198.) Cable Real Flexible Cable of Electric Shovel ?
199 / 240
(199.) Flexible cable.
200 / 240
(200.) Portable and transportable machine flexible cable in underground mines are ?
201 / 240
(201.) In the underground part in the mine, the portable & transportable machine will be operated by remote control from the respective switch having pilot core.
202 / 240
(202). If the blasting is to be done in any place within the boundary of sub-station of more than 650v or 300m from the electric supply line in the mine boundary, then who will give the permission?
203 / 240
(203.) Electricity supply shall be stopped when—
204 / 240
(204.) Apparatus Flame Proof will be at the place mentioned below in the 1st Degree Mine.
205 / 240
(205.) To what degree shall the electrical cable in mine be made, installed, precautionary, operated and maintained in such a way that the chances of open sparking are minimized.
206 / 240
(206) Sub-station limit of more than 650v in mine boundary or of power supply line. If blasting is to be done for any work within meter, then permission will be taken from the concerned Electrical Inspector.
207 / 240
(207.) The flexible cable will be connected to the machine by the following.
208 / 240
(208). There is a system of Cable Realing / Unrealing in Opencast & Underground Portable Electric Machine, then Trailing Cable will be neither of Realistic Screen nor Armouring?
209 / 240
(209). The switchgear is the most commonly used in the underground part of coal mines.
210 / 240
(210.) Trailing Cable of Dragline.
211 / 240
(211.) A.C supply system of more than 30v,
212 / 240
(212.) In each of the mines-
213 / 240
(213.) Who keeps the electrical supervisor in the mine.
214 / 240
(214.) Increased Safety 'E' Protection
215 / 240
(215.) Intrinsically safe circuit shall not allow a specified flammable gas to burn if-
216 / 240
(216) Mine Me 650 Volt. The insulation resistance of the equipment should be at least
217 / 240
(217.) Silica gel works in Power Transformer.
218 / 240
(218.)If a person's mother-in-law should continue to breathe due to electric shock. If it stops, then for how long can it be done artificially?
219 / 240
(219.) Danger notice shall be put on every such pole or tower of overhead line above 650V on which a person climbs the ladder.
220 / 240
(220). In the first shift, the Electrical Supervisor took a shut down to work on the 6.6kv Overhead Line, the work went on till the second shift and was found in the second shift, who would do the shut down.
221 / 240
(221.) An Electrical Engineer will be designated as Electrical Saftey Officer in a mine having load more than .......
222 / 240
(222). When a person comes to the connect of live electric part, then quick and automatic tripping of supply will give him electric shock.
223 / 240
(223.) Insulation Resistance of Electric Cable/Apparatus.
224 / 240
(224.) What should be the minimum resistance of the earth pit for the safety of the electrical system of the mine?
225 / 240
(225.) What type of land should not be chosen for making earth pit?
226 / 240
(226.) Earthing of Electrical Apparatus –
227 / 240
(227.) What will be the Tripping Current Maximum of Earth Leakage in U/G Mine for all installations above 250 V?
228 / 240
(228.) Filtration of Transformer Oil –
229 / 240
(229.) With sufficient clearance on all sides of the Electrical Apparatus –
230 / 240
(230.) When a 3.3 KV overhead line crosses a street, its nearest conductor should have minimum clearance from the ground?
231 / 240
(231.) Drill, Crain & Shovel has to cross Overhead Power Line, then this work –
232 / 240
(232.) Is it necessary to put credil guarding under the overhead line at such a place where the line crosses?
233 / 240
(233.) In order to protect the overhead line from electric lightning exceeding 650V –
234 / 240
(234.) Earthing the overhead line of more than 650V means.
235 / 240
(235.) Oil in Power Transformer with Oil –
236 / 240
(236.) The Single Line Circuit Diagram which is sent to the Inspector for obtaining permission to power the equipment above 650V, is
237 / 240
(237.) To take the permission of Electrical Inspector of Mine to charge power in Sub-station in Underground Mine, in Part Plan of the given Mine.
238 / 240
(238.) If more than 660V crosses the overhead Railway Line, state Highway or any public place,the Noc should be sent along with the application for charging it to Electrical Inspector of Mines.
239 / 240
(239.) Submitted in Site Teste Report for Permission Lane to Charge Apparatus, Cable, or Overhead Line above 650V.
240 / 240
(240.) Machine to Flexible Cable will be connected by-